Decision Maker: Central Sydney Planning Committee
Decision status: Recommendations Determined
Moved by the Chair (the Lord Mayor), seconded by Councillor Miller –
It is resolved that consent be granted to State Significant
Development Application D/2024/446 (SSD 65204458) subject to the conditions
detailed in Attachment B to the subject report, subject to the following
amendments (additions shown in bold italics, deletions shown in strikethrough):
Design Modifications
A19. The design of the building
must be modified as follows:
(a) All ground floor shopfronts including
awnings are to be reconstructed to interpret their original configuration and
form where possible, retaining and reusing elements of the
existing shopfronts and awnings, as outlined in the Heritage Impact Statement
prepared by Urbis (Issue 3, dated 12 February 2024) (Figure 49 in particular)
and the accompanying Schedule of Conservation Works prepared by Urbis (Issue 3
and dated 12 February 2024).
(b) The hydraulic booster is to be relocated
from the Pitt Street elevation to the northern elevation/side wall of 374 Pitt
Street at ground floor, and the historical shopfront be reconstructed.
(c) Additional vertical masonry elements are to
be included at the base of the tower, comparable to that of the design
competition scheme, providing solidity to the façade as it meets the landscape
vessel.
(d) The 2x under awning signage zones to the
Pitt Street elevation are to be amended to reduce the width of the awning
profiles from 400mm to 150mm.
(e) A clearance of 2.2 metres in width is to be
provided at ground floor level for fire egress from the doors along the
southern elevation of 362-370 Pitt Street to Pitt Street.
New and Existing Easements
A69. An Easement for Access and Fire Egress of 2
metres minimum width for a height of 4 metres, including 1 metre
minimum width, unlimited in height, and limited in stratum where
covered, must be created pursuant to Section 88B of the Conveyancing Act, 1919
prior to the issue of any Occupation Certificate. The easement must extend from
Pitt Street along Carruthers Place, to encompass all fire doors along the
southern elevation of the adjoining development to the north (SP 46628) at
362-370 Pitt Street and to Council’s satisfaction.
PART G – GOVERNMENT AGENCY CONDITIONS
Sydney Metro
Concurrence conditions as advised by Sydney Metro are as follows:
G19. All concurrence conditions
as advised by Sydney Metro for this development are to be complied with.
Prior to the
issue of a Construction Certificate
Engineering
G74 All excavation and construction works are to
be undertaken in accordance with the details, methodology, advice,
undertakings, measures and recommendations detailed in the following documents:
(a) Geotechnical
Assessment Report Rev 00 - PS138214-GEO-REP-001 prepared by WSP dated 19
December 2023.
(b) Geotechnical
Factual and Interpretive Report Rev 0 prepared by WSP dated 03/12/2024.
(c) Sydney
Metro Impact Assessment PS138214-GEO-REP-004 Rev 01 prepared by WSP dated 24
January 2025.
(d) Plan
showing Sydney Metro Reserves Drawing No PS138214-GEO-DRG-004-01 Rev A prepared
by WSP dated 15 November 2024 and verified by LTS Registered Surveyor, Georgia
Kate Rooney on 20-11-2024.
(e) Cross
Section showing Sydney Metro Reserves Drawing No PS138214-GEO-DRG-004-02 Rev A
prepared by WSP dated 15 November 2024 and verified by LTS Registered Surveyor,
Georgia Kate Rooney on 20-11-2024.
(f)
Architectural Plan Basement
1 Issue C - A0990 prepared by KHA dated 22 November 2024.
(g) Architectural
Plan Ground Floor Issue C – A1000 prepared by KHA dated 22 November 2024.
(h) Architectural
Section A (East-West) and Section B (North-South) Issue C – A2001 prepared by
KHA dated 22 November 2024.
(i)
Architectural Detailed
Section Urban Room Issue C – A2010 prepared by KHA dated 22 November 2024.
(j)
Construction methodology as
described in Section 3.4 of the Structural Detailed DA – End of Stage Report
Rev 01 - PS138214-WSP-AU-SYD-STRREP-00001 prepared by WSP, dated 22 February
2024.
(k) Appendix
F of Sydney Metro Impact Assessment Rev 01 - PS138214-GEO-REP-004 prepared by
WSP dated 24 January 2025 (Sydney Metro related risk register).
(l)
Electrolysis Report Rev A -
PS138214-AU-SYD-EB-REP-00001 prepared by WSP dated 24 January 2024.
G75 The Certifier must not issue a Construction
Certificate for the development until the Certifier has confirmed which
documents (including the versions of those documents) apply to the development
and the Certifier has confirmed in writing to Sydney Metro that the
construction drawings and specifications comply with those documents. The
Certifier must not issue a Construction Certificate for the development until
written confirmation has been received from Sydney Metro that this condition
has been satisfied.
G76 Additionally, the Certifier must not issue a
Construction Certificate for the development unless the Applicant has submitted
to Sydney Metro and Sydney Metro has provided written approval of the following
items:
(m) Current
land title including all easements, right of ways, covenants and caveats;
(n) Final
construction drawings for the Construction Certificate
(o) Structural
drawings including footing plans showing footing types, sizes, locations and
loading and excavation retention plans
(p) Updated
Impact Assessment Report PS138214-GEO-REP-004 Rev 01 prepared by WSP dated 24
January 2025 as necessary to address the following:
i.
loading from the proposed development
ii.
detail the input loads,
particularly the footing loads, applied in the numerical modelling
iii.
Section 5.3 of the report refers
to Section 6.2 of the guidelines. Specify which guideline is referred therein
iv.
provide updated excavation
retention plan with retention details, particularly for the eastern boundary
G77 Prior to the commencement of works, the
Certifier must provide written verification to Sydney Metro that this condition
has been complied with.
Rail
Corridor
G78 All structures must be designed, constructed
and maintained so as to allow for the future operation and demolition of any
part of the development without damaging or otherwise interfering with the
Sydney Metro City and Southwest rail corridor or rail operations. Where any
part of the development is to be retained because its demolition would damage
or otherwise interfere with the Sydney Metro City and Southwest rail corridor
or rail operations, that part of the development must have a minimum design life
of 100 years.
Survey
and Services
G79 Prior to the issue of a Construction
Certificate:
(a) the
Applicant must provide Sydney Metro with an accurate survey of the development
and its location relative to the rail corridor boundary and any rail
infrastructure. The survey is to be undertaken by a registered surveyor, to the
satisfaction of Sydney Metro; and
(b) a
registered surveyor shall peg-out the common property boundary between the
development site and the rail corridor and any Sydney Metro easements to ensure
that there is no encroachment by the development. A copy of the survey report
indicating the location of pegs must be provided to Sydney Metro prior to the
commencement of works.
G80 Prior to the issue of a Construction
Certificate, the Applicant must undertake a services search to establish the
existence and location of any rail services and provide the results of the
search to Sydney Metro. A services search must be based on current and not
expired information and include information obtained through the Dial Before
You Dig service. Persons performing the service search shall use equipment that
will not have any impact on rail services and signalling. Should rail services
be identified within the development site, the Applicant must discuss with
Sydney Metro whether the services are to be relocated or incorporated within
the development site.
Noise
& Vibration
G81 The development must:
(a) comply
with State Environmental Planning Policy (Transport and Infrastructure) 2021
and the NSW Department of Planning & Environment’s document titled
“Development Near Rail Corridors and Busy Roads - Interim Guideline” (2008) and
the Sydney Metro Underground Corridor Protection Guidelines (available from www.sydneymetro.info.);
(b) be
designed, constructed and maintained so as to avoid damage or other
interference which may occur as a result of air-borne noise, ground-borne noise
and vibration effects that may emanate from the rail corridor during rail
construction and operations; and
(c) not
have any noise or vibration impacts on the rail corridor or rail
infrastructure.
G82 The Applicant must updates to the DA Acoustic
Report Rev 03 - 20179-RPT-AC0003 prepared by Inhabit dated 24 May 2025 as
necessary to address the following:
(a) vibration
criteria (Section 5.3.2) in the report to be updated at to include vibration
criteria for Sydney Metro assets as listed in Sydney Metro Underground Corridor
Protection Technical Guidelines (April 2021)
(b) report
to be updated to show compliance with criteria (as listed in Sydney Metro
Underground Corridor Protection Technical Guidelines (April 2021)) can be
achieved with proposed construction equipment and methodology.
(c) noise
and vibration monitoring plan should be made available to Sydney Metro for
review prior to issuance of construction certificate
Electrolysis
G83 Prior to the issue of a Construction
Certificate, the Applicant must incorporate in the development all the measures
recommended in the electrolysis report referenced in Condition 1.1 to control
the risks to the development from electrolysis. A copy of the electrolysis
report is to be provided to the Certifier with the application for a
Construction Certificate.
G84 Prior to issuing a Construction Certificate
for the development, the Certifier must ensure that the recommendations of the
electrolysis report are incorporated in the construction drawings and
documentation.
Construction
G85 No work is permitted within the rail
corridor, or any easements which benefit Sydney Metro, at any time, unless the
prior approval of, or an Agreement with, Sydney Metro has been obtained by the
Applicant. The Certifier must not issue a Construction Certificate for the
development until written confirmation has been received from Sydney Metro that
this condition has been satisfied.
G86 No rock anchors, rock bolts, ground anchors
or rock ties, piles, foundations, rock pillars, transfer structures, basement
walls, slabs, columns, beams, cut rock faces, are to be installed in the rail
corridor, Sydney Metro property or easements. The Certifier must not issue a
Construction Certificate for the development until it has received written
confirmation from Sydney Metro that this condition has been satisfied.
G87 Prior to the issuing of a Construction
Certificate, the following information must be submitted to Sydney Metro for
review and endorsement:
(a) Machinery
to be used during excavation/construction;
(b) Demolition,
excavation and construction methodology and staging;
G88 The Certifier must not issue a Construction
Certificate for the development until it has received written confirmation from
Sydney Metro that this condition has been satisfied.
G89 If required by Sydney Metro, prior to the
issue of a Construction Certificate a Risk Assessment/Management Plan and
detailed Safe Work Method Statements for the proposed works are to be submitted
to Sydney Metro for review and endorsement regarding impacts on the rail
corridor. The Certifier must not issue a Construction Certificate for the
development until written confirmation has been received from Sydney Metro that
this condition has been satisfied.
G90 If required by Sydney Metro, a tunnel
monitoring plan (including instrumentation and the monitoring regime during
excavation and construction phases) is to be submitted to Sydney Metro for
review and endorsement prior to the issuing of a Construction Certificate. The
Certifier must not issue a Construction Certificate until written confirmation
has been received from Sydney Metro that this condition has been satisfied.
G91 Prior to the issuing of a Construction
Certificate, the Applicant must submit to Sydney Metro a plan showing all
craneage and other aerial operations for the development and must comply with
all Sydney Metro requirements. If required by Sydney Metro, the Applicant must
amend the plan showing all craneage and other aerial operations to comply with
all Sydney Metro requirements. The Certifier must not issue a Construction
Certificate for the development until written confirmation has been received
from the Sydney Metro that this condition has been satisfied.
G92 If required by Sydney Metro, prior to the
issue of a Construction Certificate the Applicant is to contact Sydney Metro's
Corridor Protection Team to determine the need for public liability insurance
cover and the level of insurance required. If insurance cover is deemed
necessary, the Applicant must obtain insurance for the sum determined by Sydney
Metro and such insurance shall not contain any exclusion in relation to works
on or near the rail corridor or rail infrastructure and must be maintained for the
period specified by Sydney Metro. Prior to issuing a Construction Certificate
for the development, the Certifier must witness written proof of any insurance
required by Sydney Metro in accordance with this condition, including the
written advice of Sydney Metro to the Applicant regarding the level of
insurance required.
Reason: construction of the
proposed development presents a risk of potential damage to the Sydney Metro -
City & Southwest Line rail corridor which is not in the public interest.
This risk of damage to public infrastructure must be appropriately managed and
mitigated.
G93 If required by Sydney Metro, prior to the
issue of a Construction Certificate the Applicant must contact the Sydney Metro
Corridor Protection Team to determine the need for the lodgement of a bond or
bank guarantee for the duration of the works and the sum of any required bond
or bank guarantee. Prior to issuing a Construction Certificate for the
development, the Certifier must witness written confirmation from Sydney Metro
that the Applicant has lodged any bond or bank guarantee required by this
condition.
Reason: construction of the
proposed development presents a risk of potential damage to the Sydney Metro -
City & Southwest Line rail corridor which is not in the public interest.
This risk of damage to public infrastructure must be appropriately managed and
mitigated.
G94 Prior to the issue of a Construction
Certificate, the Applicant must prepare and provide to Sydney Metro for review
and endorsement a hydrogeologic assessment report demonstrating that any
dewatering during construction will not have any adverse settlement impacts on
the rail corridor. The Certifier must not issue a Construction Certificate
until this report has been endorsed by Sydney Metro in writing.
G95 Prior to the issue of a Construction
Certificate, the Applicant must prepare and provide to Sydney Metro for review
of a Construction Traffic Management Plan to ensure no adverse impacts to
Sydney Metro operations. The Certifier must not issue a Construction
Certificate until this Plan has been endorsed by Sydney Metro in writing.
G96 Prior to the issue of a Construction
Certificate, any proposed alterations to Sydney Metro assets must be approved
by Sydney Metro and any proposed changes may be subject to operator
requirements. The Certifier must not issue a Construction Certificate until
Sydney Metro approval has been provided in writing.
Documentation
G97 Copies of any certificates, drawings,
approvals or documents endorsed by, given to or issued by Sydney Metro must be
submitted to Council for its records prior to the issue of any Construction
Certificate.
During
Construction
Supervision
G98 Unless advised by Sydney Metro in writing,
all excavation, shoring and piling works within 25m of the rail corridor are to
be supervised by a geotechnical engineer experienced with such excavation
projects and who holds current professional indemnity insurance.
Consultation
G99 The Applicant must ensure that at all times
they have a representative (which has been notified to Sydney Metro in
writing), who:
(a) oversees
the carrying out of the Applicant’s obligations under the conditions of this
consent and in accordance with correspondence issued by Sydney Metro;
(b) acts
as the authorised representative of the Applicant; and
(c) is
available (or has a delegate notified in writing to Sydney Metro that is
available) on a 7 day a week basis to liaise with the representative of Sydney
Metro as notified to the Applicant.
G100 Without in any way limiting the operation of
any other condition of this consent, the Applicant must, during demolition,
excavation and construction works, consult in good faith with Sydney Metro in
relation to the carrying out of the development works and must respond or
provide documentation as soon as practicable to any queries raised by Sydney
Metro in relation to the works.
G101 Where a condition of consent requires consultation
with Sydney Metro, the Applicant shall forward all requests and/or
documentation to the relevant Sydney Metro interface team.
Drainage
G102 The Applicant must ensure that all existing and
future drainage works on the development site will be directed into the
appropriate local council or approved drainage system.
G103 The Applicant must ensure that during works no
water collects on or near the railway corridor. Should water be allowed to pond
adjacent to rail infrastructure facilities and service is interrupted, the
Applicant shall be liable for any Sydney Metro expenditure involved with
restoring or maintaining alternative services.
Inspections
G104 If required by Sydney Metro, the Applicant must
give Sydney Metro written notice at least 5 business days before any of the
following events occur within 25 metres of the rail corridor:
(a) site
investigations;
(b) foundation,
pile and anchor set out;
(c) set
out of any other structures below ground surface level or structures which will
transfer any load or bearing;
(d) foundation,
pile and anchor excavation;
(e) other
excavation;
(f) surveying
of foundation, pile and anchor excavation and surveying of as-built
excavations;
(g) other
concreting; or
(h) any
other event that Sydney Metro has notified to the Applicant in writing
so that Sydney Metro may
inspect the carrying out or completion of those works on the development site.
G105 If required by Sydney Metro, prior to the
commencement of works or at any time during the excavation and construction
period deemed necessary by Sydney Metro, a joint inspection of the rail
infrastructure and property in the vicinity of the development is to be carried
out by representatives from Sydney Metro and the Applicant and a dilapidation
survey prepared. The dilapidation survey(s) will establish the extent of any
existing damage and enable any deterioration during construction to be observed
and rectified at the Applicant’s cost. The submission of a detailed
dilapidation report by the Applicant for review and approval by Sydney Metro
will be required within 10 days following the undertaking of any joint
inspection, unless otherwise notified by Sydney Metro in writing.
Prior
to the issue of an Occupation Certificate
Noise
and Vibration
G106 Prior to the issue of an Occupation
Certificate, an acoustic assessment report must be prepared and submitted to
the Certifying Authority, Council and Sydney Metro certifying that the
completed development meets the requirements of:
(a) State
Environmental Planning Policy (Transport and Infrastructure) 2021;
(b) the
Department of Planning, Infrastructure and Environment’s Development Assessment
Guideline titled “Development Near Rail Corridors and Busy Roads - Interim
Guidelines”; and
(c) any
other noise and vibration requirements imposed by this consent.
G107 The acoustic report must demonstrate testing of
external and internal noise levels for the completed development and ensure
that external noise levels are representative of the typical maximum levels
that may occur at the development and internal noise levels meet the required
dB(A) levels. Where it is found that internal noise levels are greater than the
required dB(A) level, necessary corrective measures must be carried out to
ensure that internal noise levels are compliant with the requirements of this
consent.
Documentation
G108 Prior to the issue of an Occupation
Certificate, the Applicant is to submit as-built drawings to Sydney Metro and
Council. The as-built drawings are to be endorsed by a registered surveyor
confirming that there has been no encroachment into the rail corridor or Sydney
Metro easements, unless agreed to by Sydney Metro in writing. The Certifier
must not issue an Occupation Certificate until written confirmation has been
received from Sydney Metro that this condition has been satisfied.
G109 Copies of any certificates, drawings, approvals
or documents endorsed by, given to or issued by Sydney Metro must be submitted
to Council for its records prior to the issue of any Occupation Certificate.
Inspections
G110 If required by Sydney Metro, prior to the issue
of an Occupation Certificate, a joint inspection of the rail infrastructure and
property in the vicinity of the development is to be carried out by
representatives from Sydney Metro and the Applicant and a dilapidation survey
prepared. The dilapidation survey will establish the extent of any existing
damage and enable any deterioration during operation of the development to be
observed. The Certifier is not to issue an Occupation Certificate for the development
until written confirmation has been received from Sydney Metro that this
condition has been satisfied.
G111 At any time during the use and occupation of
the development, Sydney Metro may also require a joint inspection of the rail
infrastructure and property in the vicinity of the development by
representatives from Sydney Metro and the Applicant and a dilapidation survey
prepared. Any such dilapidation survey will establish the extent of any damage
or deterioration during operation of the development to be observed and
rectified at the Applicant’s cost.
General
Inspections
G112 At any time during the construction of the
development, Sydney Metro and persons authorised by those entities may give
reasonable notice to the Applicant or the Applicant’s principal contractor that
Sydney Metro or persons authorised by that entity seek to:
(a) inspect
the development site and all works and structures that may impact on the rail
corridor, including at specified “hold points” in the construction of the
development; and
(b) attend
on-site meetings with the Applicant and its contractors,
to enable Sydney Metro to
determine whether the development has been or is being constructed and
maintained in accordance with all approved plans and this development consent.
Other
G113 Any conditions or other requirements imposed by
Sydney Metro part of its approval/endorsement of any documents provided by the
Applicant to Sydney Metro in accordance with these conditions of consent must
also be complied with by the Applicant when implementing any approved/endorsed
documents, plans, reports during the construction and operation of the
development (as applicable).
G114 Where a condition of consent requires Sydney
Metro endorsement or approval, the Certifier must not to issue a Construction
Certificate or Occupancy Certificate, as the case may be, until written
confirmation has been received from those entities that the particular
condition has been complied with. The issuing of staged Construction
Certificates by the Certifier dealing with specific works and compliance
conditions can only occur subject to written confirmation from Sydney Metro.
G115 All reasonable Sydney Metro costs associated
with review of plans, designs and legal must be borne by the applicant.
The application was approved for the following reasons:
(A) The proposal is consistent with the strategic planning framework by providing a high-quality mixed-use development in the City including new hotel accommodation and commercial floor space.
(B) The applicant has undertaken a competitive design process in accordance with the City's policy, to which the proposed development is generally consistent. The applicant has adequately responded to the recommendations of the competition jury.
(C) The development complies with the maximum height, floor space ratio and car parking controls contained in the Sydney Local Environmental Plan 2012.
(D) The application demonstrates design excellence in accordance with the provisions of Clause 6.21C of the Sydney Local Environmental Plan 2012. The slim tower design, materiality and siting contribute to the skyline and relate positively to the surrounding context. Sufficient separation is provided to maintain a good standard of amenity for adjoining properties and the public domain. The tower results in acceptable environmental impacts and achieves a good standard of environmental performance. The development provides landscaping on podiums which will contribute to local biodiversity and visual amenity. The development provides adequate bike parking for employees to the site and is suitably located close to good public transport.
(E) The proposed construction methodology and design responds appropriately to the surrounding heritage context and does not adversely affect adjoining heritage items.
(F) The development is anticipated to create 570 construction and 400 ongoing operational jobs.
(G) The development has provided sufficient information to address the Secretary's Environmental Assessment Requirements.
(H) All other issues have been appropriately addressed by recommended conditions of consent.
(I) Condition A19(a) was amended to provide a level of flexibility to the interpretation of the shopfront.
(J) Condition A19(e) was added to increase the clearance for the fire escape.
(K) Condition A69 was amended to align the easements with the changes to Condition A19(e).
(L) Conditions G74 to G115 were added as required by the Sydney Metro concurrence.
Carried unanimously.
D/2024/446
Report author: Jessica Symons
Publication date: 15/05/2025
Date of decision: 08/05/2025
Decided at meeting: 08/05/2025 - Central Sydney Planning Committee
Accompanying Documents: