Decision Maker: Local Pedestrian, Cycling, Traffic Calming and Transport Forum
Decision status: Recommendations Determined
2025/595268
Recommendation
It is recommended that the Committee review the
temporary road
(A) The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.
(B) The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.
(C) The Applicant has indicated the 3-5 November 2025 as contingency dates.
(D) The
Applicant must contact the
(E) The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.
(F) The
Applicant must provide a telephone number of the supervisor responsible for the
proposed
(G) The
Applicant must contact relevant Bus Operators and arrange and pay for the
rerouting of bus services around the
Advice
The Committee raised no issues with this Item.
Background
Justus Group Pty Ltd has applied for the temporary road
Report author: Claudia Calabro
Publication date: 16/10/2025
Date of decision: 16/10/2025
Decided at meeting: 16/10/2025 - Local Pedestrian, Cycling, Traffic Calming and Transport Forum
Accompanying Documents: