Mobile Crane - Temporary Road Closures - Ebsworth Street, Zetland

Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee

Decision status: Recommendations Determined

Decisions:

2018/354461

Recommendation

It is recommended that the Committee endorse the temporary road closures of Ebsworth Street, Zetland, between Bourke Street and Tweed Place, from 6.30am on Tuesday 4 September 2018 to 5.30pm on Thursday 6 September 2018, and from 6.30am on Thursday 4 October 2018 to 5.30pm on Saturday 6 October 2018, subject to the following conditions:

(A)      The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.

(B)      The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.

(C)      The Applicant has indicated from 6.30am on Friday 7 September 2018 to 5.30pm on Saturday 8 September 2018, and from 6.30am on Sunday 7 October 2018 to 5.30pm on Monday 8 October 2018 as contingency dates.

(D)      The Applicant must contact the Redfern PAC to discuss deployment of user pay police for the road closures.

(E)      The Applicant must provide a telephone number of the supervisor responsible for the proposed closures and include contact details in the notification letters to be distributed to affected stakeholders.

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Roads and Maritime Services

ü

 

NSW Police – Redfern PAC

ü

 

Representative for the Member for Heffron

ü

 

 

 

Decision

The Committee carried the recommendation unanimously and noted the change of date from:

·         6.30am on Tuesday 4 September 2018 to 5.30pm on Thursday 6 September 2018, and from 6.30am on Thursday 4 October 2018 to 5.30pm on Saturday 6 October 2018.

Backup date: 6.30am on Friday 7 September 2018 to 5.30pm on Saturday 8 September 2018, and 6.30am on Sunday 7 October 2018 to 5.30pm on Monday 8 October 2018

 to:

·         from 6.30am on Wednesday 24 October 2018 to 5.30pm on Wednesday 31 October 2018

Backup dates from 6.30am Thursday 1 November to 5.30pm 8 November 2018

·         from 6.30am Wednesday 14  November 2018 to 5.30pm 15 November 2018.

Backup dates 6.30am Wednesday 21 November 2018 to 5.30pm Thursday 22 November 2018

 

Background

Crown Group Constructions Pty Ltd has applied for the temporary road closures of Ebsworth Street, Zetland, between Bourke Street and Tweed Place, from 6.30am on Tuesday 4 September 2018 to 5.30pm on Thursday 6 September 2018, and from 6.30am on Thursday 4 October 2018 to 5.30pm on Saturday 6 October 2018.

Report author: Tony Ly

Publication date: 16/08/2018

Date of decision: 16/08/2018

Decided at meeting: 16/08/2018 - Local Pedestrian, Cycling and Traffic Calming Committee