Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee
Decision status: Recommendations Determined
X023793.010
Recommendation
It is recommended that the Committee endorse the
temporary road
(A) The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.
(B) The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.
(C)
The Applicant must contact the
(D) The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.
(E)
The Applicant must provide a telephone number of
the supervisor responsible for the proposed
(F) Access on the viaduct is to be maintained at all times for Sydney Buses and emergency vehicles.
Voting
Members for this Item
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Roads and Maritime Services |
ü |
|
NSW Police – |
ü |
|
Representative for the Member for |
ü |
|
Decision
The Committee carried the recommendation unanimously.
Background
Haslin Construction Pty Ltd has applied for the temporary
road closure of the Burton Street viaduct, Darlinghurst, between Liverpool and
West Streets (two lanes), for six months. Access on the viaduct is to be
maintained at all times for Sydney Buses and emergency vehicles.
Report author: Clement Lim
Publication date: 18/04/2019
Date of decision: 18/04/2019
Decided at meeting: 18/04/2019 - Local Pedestrian, Cycling and Traffic Calming Committee