Decision Maker: Local Planning Panel
Decision status: Recommendations Determined
The Panel:
(A) upheld the variation requested to Clause 4.3 'Height of buildings' in accordance with Clause 4.6 'Exceptions to development standards' of the Sydney Local Environmental Plan 2012; and
(B) granted
consent to Development Application Number strikethrough):
PART
A - GENERAL
(25) (7) ASBESTOS REMOVAL WORKS
All works removing asbestos containing materials must be carried out by a suitably licensed asbestos removalist duly licensed with SafeWork NSW, holding either a Friable (Class A) or a Non-Friable (Class B) Asbestos Removal Licence which ever applies.
A copy of the relevant licence must be made available to any authorised Council officer on request within 24 hours.
Reason
To ensure that the handling and removal of asbestos from the site is appropriately managed.
Remaining
conditions to be renumbered accordingly.
(22)
(8) PHOTOGRAPHIC ARCHIVAL RECORDING
A photographic archival recording must be prepared prior to the commencement of works / during works / at the completion of works. A copy of the photographic archival recording prepared in accordance with the Heritage NSW publication ‘Guidelines for preparing archival recordings of heritage items as a condition of consent’ (2025) is to be submitted for approval by the Area Planning Manager/Heritage and Urban Design Manager prior to issue of an Occupation Certificate.
Reason
To ensure appropriate archival documentation of the building.
Remaining
conditions to be renumbered accordingly.
PART B - BEFORE ISSUE
OF A CONSTRUCTION CERTIFICATE
(9)
DEMOLITION, EXCAVATION AND CONSTRUCTION MANAGEMENT
a) Prior
to the commencement of demolition and/or excavation work the following details
must be submitted to and be approved by the Principal Certifier:
i.
Plans and elevations showing
distances of the subject building from the location of adjoining and
common/party walls, and (where applicable) the proposed method of facade
retention.
ii.
A Demolition Work Method Statement
prepared by a licensed demolisher who is registered with SafeWork NSW. (The
demolition by induced collapse, the use of explosives or on-site burning is not
permitted.)
iii.
An Excavation Work Method
Statement prepared by an appropriately qualified person.
iv.
A Waste and Recycling Management Plan
– Demolition and Construction for the demolition and or excavation of the
proposed development. The plan is to include details of materials that will be
excavated and their proposed destination or reuse.
v.
Plans and elevations showing the
location, construction and installation of temporary site fencing and any
construction related temporary structures placed on and/or above roads used in
connection with the development.
Note:
Construction related temporary structures, including hoardings and scaffolding,
proposed for erection on and/or above City-owned and controlled land (footways
and roadways), and other activities, must comply with Council’s Code of
Practice: Construction related Temporary Structures On and Above Roads and the
Code of Practice: Hoisting and Construction Activities On and Above Roads
including obtaining all required approvals from Council under the provisions of
the Local Government Act 1993 and the Roads Act 1993 prior to installation.
b) Such
statements must, where applicable, be in compliance with AS2601-2001 Demolition
of Structures, the Work, Health and Safety Act 2011 and Regulation; Council’s
Guidelines for Waste Management in New Developments 2018, the Waste Avoidance
and Resource Recovery Act 2001, and all other relevant acts and regulations and
must include provisions for:
i.
A Materials Handling Statement for
the removal of refuse from the site in accordance with the Waste Avoidance and
Resource Recovery Act 2001.
ii.
The name and address of the
company/contractor undertaking demolition/excavation works.
iii.
The name and address of the
company/contractor undertaking off site remediation/disposal of excavated
materials.
iv.
The name and address of the
transport contractor.
v.
The type and quantity of material
to be removed from site.
vi.
Location and method of waste
disposal and recycling.
vii.
Proposed truck routes, in
accordance with this development consent.
viii.
Procedures to be adopted for the
prevention of loose or contaminated material, spoil, dust and litter from being
deposited onto the public way from trucks and associated equipment and the
proposed method of cleaning surrounding roadways from such deposits. (Note:
With regard to demolition of buildings, dust emission must be minimised for the
full height of the building. A minimum requirement is that perimeter
scaffolding, combined with chain wire and shade cloth must be used, together
with continuous water spray during the demolition process. Compressed air must
not be used to blow dust from the building site).
ix.
Measures to control noise
emissions from the site.
x.
Measures to suppress odours.
xi.
Enclosing and making the site
safe.
xii.
Induction training for on-site
personnel.
xiii.
Written confirmation that an
appropriately qualified Occupational Hygiene Consultant has inspected the
building/site for asbestos, contamination and other hazardous materials, in
accordance with the procedures acceptable to SafeWork NSW.
xiv.
An Asbestos and Hazardous
Materials Clearance Certificate by a person approved by the SafeWork NSW.
xv.
Disconnection of utilities.
xvi.
Fire Fighting. (Fire fighting
services on site are to be maintained at all times during demolition work.
Access to fire services in the street must not be obstructed).
xvii.
Access and egress. (Demolition and
excavation activity must not cause damage to or adversely affect the safe
access and egress of the subject building or any adjacent buildings).
xviii.
Waterproofing of any exposed
surfaces of adjoining buildings.
xix.
Control of water pollution and
leachate and cleaning of vehicles tyres (proposals must be in accordance with
the Protection of the Environmental Operations Act 1997).
xx.
Working hours, in accordance with
this development consent.
xxi.
Any SafeWork NSW requirements.
c) The
approved work method statements and a waste management plan as required by this
condition must be implemented in full during the period of construction.
d) All
waste records from the recycling and/or disposal of any demolition and
construction waste generated from the works must be retained on site. These records
must be available for sighting on request by an authorised Council officer.
Reason
To ensure
that impacts arising from demolition, excavation and construction are
appropriately managed.
Remaining
conditions to be renumbered accordingly.
The application was approved for the following reasons:
(A) The proposed development is consistent with the objectives of the MU1 Mixed Use zone and the retention of the existing commercial office use is permissible with consent in the zone.
(B) The proposed development satisfies the relevant objectives, aims and provisions of the Sydney LEP and the Sydney DCP.
(C) The proposed development satisfies the heritage conservation requirements under the Heritage Act 1977, Sydney LEP, Sydney DCP for the building and surrounding site curtilage which are listed on the state heritage register, as a heritage item under the Sydney LEP and as a contributing building to the Cleveland Gardens heritage conservation area (C62) under the Sydney LEP.
(D) The proposed development exhibits design excellence having considered the matters in Clause 6.21C of the Sydney LEP.
(E) Based
upon the material available to the
(F) The
proposal is in the public interest as it is consistent with the objectives of
the
(G) The asbestos removal and photographic archival recording conditions were moved to general conditions, rather than prior to the issue of an occupation certificate.
(H) Condition 9 was added to ensure that impacts arising from demolition, excavation and construction are appropriately managed.
Carried unanimously.
D/2026/64
Report author: Costa Dantos
Publication date: 25/05/2026
Date of decision: 20/05/2026
Decided at meeting: 20/05/2026 - Local Planning Panel
Accompanying Documents: