Project Scope - Elizabeth Street and Randle Street Cycleway

Decision Maker: Council

Decision status: Recommendations Determined

Purpose:

The City intends to construct a separated cycleway along the western side of Elizabeth Street between Eddy Avenue and Randle Street and along Randle Street between Elizabeth Street and Devonshire Street.
The new cycleway will connect the separated cycleway on Eddy Avenue with the Surry Hills to Central Quietway and Prince Alfred Park. It will separate bike riders and pedestrians at the Central Station exit near Foveaux Street and provide an alternative route to the busy Chalmers Street with its Light Rail and Metro interface.

Decision:

It is resolved that Council:

(A)      approve the project scope for the Elizabeth Street and Randle Street cycleway as shown in Attachment A to the subject report for progression to detailed design and submission of a grant application for construction funding under the Get NSW Active program;

(A)      note the financial implications detailed in the subject report; and

(B)      note that the construction of the project is subject to the City receiving grant funding.

Carried unanimously.

X102094

 

Report author: James Kidd

Publication date: 29/06/2026

Date of decision: 29/06/2026

Decided at meeting: 29/06/2026 - Council