chevron-rightcancelexternal-link

Works Zone - Sussex Street, Sydney

Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee

Decision status: Recommendations Determined

Decisions:

2018/382913

Recommendation

It is recommended that the Committee endorse the temporary reallocation of the footpath on the eastern side of Sussex Street, Sydney, between the points 20 metres and 45 metres north of Bathurst Street as "Works Zone 7am-7pm Mon-Fri 7am-5pm Sat", subject to the following conditions:

(A)      The Applicant must comply with the Works Zone conditions as stipulated in Schedule C of this agenda.

(B)      The Applicant must obtain separate approval from the City's Tree Management Team prior to implementation of the Works Zone.

(C)      The Applicant is not permitted to operate any part of a crane over a public road or hoist/swing goods from a Works Zone across or over any part of a public road by means of a lift, hoist or crane unless a separate approval has been obtained from the City's Construction and Building Certification Services Unit as required under Section 68 of the Local Government Act 1993 and Section 138 of the Roads Act 1993.

(D)      The Applicant must temporarily remove the kerb and footpath so that an indented Works Zone on the footpath can be installed. The removed kerb must be delivered undamaged and stored at the City’s Depot. At the completion of the project, the Applicant must reinstate the original kerb and footpath to the satisfaction of the City.

(E)      The Applicant must notify adjacent properties of the Works Zone at least seven 14 days prior to installation.

(F)       The Applicant must provide a telephone number of the Site Manager.

 

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Roads and Maritime Services

ü

 

NSW Police – Sydney City PAC

ü

 

Representative for the Member for Sydney

ü

 

 

Decision

The Committee carried the recommendation unanimously.

Background

On 13 December 2017, the Committee endorsed a 25 metre Works Zone in the kerb space of Sussex Street to facilitate works at 286-296 Suusex Street.

On 21 June 2018, the Committee endorsed the relocation of the Works Zone to the footpath of Sussex Street and operate from 7am to 5pm, Monday to Saturday.

Parkview Constructions Pty Ltd has applied to extend the operating times of the Works Zone from 7am to 7pm, Monday to Friday and 7am to 5pm on Saturdays.

Report author: Tony Ly

Publication date: 16/08/2018

Date of decision: 16/08/2018

Decided at meeting: 16/08/2018 - Local Pedestrian, Cycling and Traffic Calming Committee

Accompanying Documents: