chevron-rightcancelexternal-link

Works Zone - Garden Street, Alexandria

Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee

Decision status: Recommendations Determined

Decisions:

2018/366028

Recommendation

It is recommended that the Committee endorse the reallocation of the kerb space on the eastern side of Garden Street, Alexandria, between the points 13.2 metres and 32.7 metres north of Henderson Road, as "Works Zone 7.30am-5.30pm Mon-Fri, 7.30am-3.30pm Sat" and "No Stopping Other Times", subject to the following conditions:

(A)      The Applicant must comply with the Works Zone conditions as stipulated in Schedule C of this agenda.

(B)      The Applicant must obtain separate approval from the City's Tree Management Team prior to implementation of the Works Zone.

(C)      The Applicant is not permitted to operate any part of a crane over a public road or hoist/swing goods from a Works Zone across or over any part of a public road by means of a lift, hoist or crane unless a separate approval has been obtained from the City's Construction and Building Certification Services Unit as required under Section 68 of the Local Government Act 1993 and Section 138 of the Roads Act 1993.

(D)      The Applicant must use RMS-Accredited Traffic Controllers to manage traffic and pedestrian flows at the intersection of Garden Street and Henderson Road when the Works Zone is in use.

(E)      The Applicant is to obtain a Road Occupancy License from the Transport Management Centre prior to the commencement of works.

(F)       The Applicant must notify adjacent properties of the Works Zone at least 14 days prior to installation.

(G)      The Applicant must provide a telephone number of the Site Manager.

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Roads and Maritime Services

ü

 

NSW Police – Redfern PAC

ü

 

Representative for the Member for Newtown

ü

 

 

 

Decision

The Committee carried the recommendation unanimously.

Background

Australex Group Pty Ltd has requested a 19.5 metre long Works Zone in Garden Street, Alexandria.

The Works Zone is to facilitate construction works at 50 Garden Street, for a period of approximately 26 weeks.

Report author: Tony Ly

Publication date: 20/09/2018

Date of decision: 20/09/2018

Decided at meeting: 20/09/2018 - Local Pedestrian, Cycling and Traffic Calming Committee

Accompanying Documents: