Exemption from Tender and Contract Variation - Head Design Consultant – Perry Park Stage 2

Decision Maker: Council

Decision status: Recommendations Determined

Decision:

Moved by Councillor Scully, seconded by Councillor Thalis -

It is resolved that:

(A)      Council approve an exemption from tender for Perry Park Stage 2 for additional contract contingency to allow for extended construction and post construction stage services;

(B)      Council note that a satisfactory result would not be achieved by inviting tenders for this work because the consultant is already engaged, and work is well underway; and

(C)      authority be delegated to the Chief Executive Officer to negotiate, execute and administer/vary the contracts relating to Perry Park Stage 2.

Carried unanimously.

X021328

 

Report author: Erin Cashman

Publication date: 26/10/2020

Date of decision: 26/10/2020

Decided at meeting: 26/10/2020 - Council