Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee
Decision status: Recommendations Determined
2021/141143
Recommendation
It is recommended that the Committee endorse the
temporary road
(A) The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.
(B) The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.
(C) The Applicant has indicated the 3,4,10 and 11 July 2021 as contingency dates.
(D)
The Applicant must contact the
(E) The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.
(F)
The Applicant must provide a telephone number of
the supervisor responsible for the proposed
(G)
The Applicant must contact Sydney Buses and
arrange and pay for the rerouting of bus services around the
Voting
Members for this Item
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Transport for NSW |
ü |
|
NSW Police – |
ü |
|
Representative for the Member for |
ü |
Advice
The Committee
unanimously supported the recommendation and noted the change of date for the
Temporary Road Closure – Gresham Street, Sydney between Bridge Street and
Spring Street, Sydney as follows:
From:
·
12:01am Saturday 19 June to midnight on Saturday 19
June 2021, with contingency dates of 3,4,10 and 11 July 2021
To:
·
12:01am Saturday 25 September to midnight Sunday 26
September 2021 with contingency dates of 16 and 17 October 2021 – Grillage
Installation
·
12:01am Saturday 9 October to midnight Sunday 10
October 2021 with contingency dates of 23 and 24 October 2021 – Crane
Installation
Background
Adams Traffic Management Services has applied for the
temporary road
Report author: Claudia Calabro
Publication date: 20/05/2021
Date of decision: 20/05/2021
Decided at meeting: 20/05/2021 - Local Pedestrian, Cycling and Traffic Calming Committee
Accompanying Documents: