Road Works - Temporary Road Closure - Macdonald Street, Erskineville

Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee

Decision status: Recommendations Determined

Decisions:

2021/226482

Recommendation

It is recommended that the Committee endorse the temporary road closures between 18 September 2021 to 28 February 2022 inclusive, on the following streets in Erskineville:

·            Macdonald Street, between Bridge and Hadfields Streets;

·            Zenith Street, between Metters and MacDonald Streets;

·            Pearl Street, between Metters and Macdonald Streets;

·            Eve Street, between MacDonald Street and Brightwell Lane; and

·            Goddard Street, south of Macdonald Street.

subject to the following conditions:

(A)       The Applicant must comply with the temporary road closure conditions as mentioned Schedule B of this agenda.

(B)       The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.

(C)       The Applicant must contact the South Sydney PAC to discuss deployment of user pay police for the road closures.

(D)       The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.

(E)       The Applicant must provide a telephone number of the supervisor responsible for the proposed closure and include contact details in the notification letters to be distributed to affected stakeholders.

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Transport for NSW

ü

 

NSW Police – South Sydney PAC

ü

 

Representative for the Member for Heffron

ü

 

 

Advice

The Committee unanimously supported the recommendation.

 

Background

On 15 October 2020, the Committee endorsed the road closures around Macdonald Street, Erskineville between Monday 26 October 2020 and 17 September 2021. Ward Civil & Environmental Engineering Pty Ltd has applied to extend the period of the closures to 28 February 2022 to allow for the completion of the works which have been delayed due to unexpected latent conditions in the ground.

Report author: Brian Jacobs

Publication date: 17/06/2021

Date of decision: 17/06/2021

Decided at meeting: 17/06/2021 - Local Pedestrian, Cycling and Traffic Calming Committee

Accompanying Documents: