Decision Maker: Central Sydney Planning Committee
Decision status: Recommendations Determined
Moved by the Chair, seconded by Councillor Scully –
It is resolved that:
(A) the variation requested to Clause 4.3 'height of buildings' in accordance with Clause 4.6 'exceptions to development standards' of Sydney Local Environmental Plan 2012 be upheld; and
(B) consent
be granted to Development Application No.
The application was approved for the following reasons:
(A)
The proposal
satisfies the objectives of the Environmental Planning and Assessment Act 1979
in that, subject to the imposition of conditions as recommended, it achieves
the objectives of the planning controls for the site for the reasons outlined
in the report to the Central Sydney Planning Committee.
(B)
The proposal
generally satisfies the objectives and relevant provisions of the Sydney Local
Environmental Plan 2012 and the Sydney Development Control Plan 2012. Where
non-compliances exist, they have been demonstrated to be acceptable in the
circumstances of the case or can be resolved by the recommended conditions of
consent.
(C)
Based upon
the material available to the Central Sydney Planning Committee at the time of
determining this application, the Committee is satisfied that:
(i)
The
applicant’s written request has adequately addressed the matters required to be
demonstrated by Clause 4.6(3) of the Sydney Local Environmental Plan 2012, that
compliance with the 'height of building' development standard is unreasonable
or unnecessary and that there are sufficient planning grounds to justify
contravening Clause 4.3 of the Sydney Local Environmental Plan 2012.
(ii)
The proposal
is in the public interest because it is consistent with the objectives of the
B7 Business Park zone and the 'height of building' development standard.
(D) The development is consistent with the amended concept approval for the site, being D/2019/686/A and the executed Voluntary Planning Agreement (VPA/2019/16).
Carried unanimously.
D/2021/529
Report author: Bryan Li
Publication date: 12/11/2021
Date of decision: 11/11/2021
Decided at meeting: 11/11/2021 - Central Sydney Planning Committee