Works Zone - Griffin Place, Glebe

Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee

Decision status: Recommendations Determined

Decisions:

2022/055042

Recommendation

It is recommended that the Committee endorse the reallocation of the kerb space on the eastern side of Griffin Place, Glebe between the points 113 metres and 128 metres north of Forsyth Street as "Works Zone 7.30am-5.30pm Mon-Fri 7.30am-3.30pm Sat", subject to the following conditions:

(A)      The Applicant must comply with the Works Zone conditions as stipulated in Schedule C of this agenda.

(B)      The Applicant is not permitted to operate any part of a crane over a public road or hoist/swing goods from a Works Zone across or over any part of a public road by means of a lift, hoist or crane unless a separate approval has been obtained from the City's Construction and Building Certification Services Unit as required under Section 68 of the Local Government Act 1993 and Section 138 of the Roads Act 1993.

(C)      The Applicant must notify adjacent properties of the Works Zone at least 14 days prior to installation and must provide a telephone number of the supervisor responsible for the proposed Works Zone and include contact details in the notification letter to be distributed to affected stakeholders.

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

         ü

 

Transport for NSW

         ü

 

NSW Police – Leichhardt PAC

         ü

 

Representative for the Member for Balmain

         ü

 

 

Advice

The Committee unanimously supported the recommendation.

Background

PD Remedial Pty Ltd has requested a 15 metre long Works Zone in Griffin Place, Glebe.

The Works Zone is to facilitate construction works at 27 Griffin Place, Glebe.

Report author: Ganesh Vengadasalam

Publication date: 17/03/2022

Date of decision: 17/03/2022

Decided at meeting: 17/03/2022 - Local Pedestrian, Cycling and Traffic Calming Committee