Mobile Crane - Temporary Road Closure - Stanley and College Streets Darlinghurst

Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee

Decision status: Recommendations Determined

Decisions:

2022/316821

Recommendation

It is recommended that the Committee endorse the temporary road closure of Stanley Street, Darlinghurst, between College Street and Young Street, (four lanes), and the southbound traffic lanes of College Street between William Street to Francis Street (four lanes) from 8pm on Saturday 24 September 2022 to 6am on Sunday 25 September 2022, and from 8pm on Saturday 1 October 2022 to 6am Sunday 2 October 2022, subject to the following conditions:

(A)      The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.

(B)      The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.

(C)      The Applicant has indicated the 8-9,15-16,22-23, and 29-30 October 2022 and 5-6 November 2022 as contingency dates.

(D)      The Applicant must contact the Kings Cross PAC to discuss deployment of user pay police for the road closure.

(E)      The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.

(F)       The Applicant must provide a telephone number of the supervisor responsible for the proposed closure and include contact details in the notification letters to be distributed to affected stakeholders.

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Transport for NSW

ü

 

NSW Police – Kings Cross PAC

ü

 

Representative for the Member for Sydney

ü

 

 

Advice

The Committee unanimously supported the recommendation.

Background

Bellevarde Constructions has applied for the temporary road closure of Stanley Street, Darlinghurst, between College Street and Young Street, (four lanes), and the southbound traffic lanes of College Street between William Street to Francis Street (four lanes) from 8pm on Saturday 24 September 2022 to 6am on Sunday 25 September 2022, and from 8pm on Saturday 1 October 2022 to 6am Sunday 2 October 2022.

It should be noted only northbound traffic will be allowed through on College Street during the closure.

Report author: Claudia Calabro

Publication date: 18/08/2022

Date of decision: 18/08/2022

Decided at meeting: 18/08/2022 - Local Pedestrian, Cycling and Traffic Calming Committee

Accompanying Documents: