It is recommended that the Committee endorse the
temporary road
(A) The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.
(B) The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.
(C) The Applicant has indicated the 3 to 4 December 2022 as contingency dates.
(D) The
Applicant must contact the
(E) The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.
(F) The
Applicant must provide a telephone number of the supervisor responsible for the
proposed
Voting Members for this Item
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Transport for NSW |
ü |
|
NSW Police – |
ü |
|
Representative for the Member for |
ü |
|
Advice
The Committee unanimously supported the recommendation and
noted the change to the detour plan.
Background
Paynter Dixon has applied for the temporary road
The proposed temporary road
The Applicant has provided a site-specific Traffic
Control Plan that includes details of barricades, signs, flagmen and other
traffic devices to implement the proposed road
There are currently no other approved temporary road closures proposed to take place on the same day in this area.
The temporary road
A Traffic Management Plan (TMP) for the temporary road closure was approved by Transport for NSW (TFNSW).
The Applicant will be required to notify affected stakeholders as stipulated in Schedule B.
All costs associated with the proposed
claudia calabro, traffic works coordinator