Decision Maker: Local Planning Panel
Decision status: Recommendations Determined
The Panel granted deferred commencement consent to
Development Application No. strikethrough):
(1) CONSERVATION
MANAGEMENT PLAN
(a)
Condition
No. 119(a), under Consent No. D/2016/476 (as may be amended), in
so far it requires NSW Heritage Council’s endorsement of a Conservation
Management Plan and the approval of a schedule of conservation works must be
satisfied prior to activation of this consent.
(b)
Evidence
that will sufficiently enable Council to be satisfied as to those matters
identified in deferred commencement conditions, as indicated above, must be
submitted to Council within 12 months of the date of determination of this
deferred commencement consent failing which, this deferred development consent
will lapse pursuant to section 4.53(6) of the Environmental Planning and
Assessment Act, 1979.
(c)
The
consent will not operate until such time that the Council notifies the
Applicant in writing that deferred commencement consent conditions, as
indicated above, have been satisfied.
(d)
Upon
Council giving written notification to the Applicant that the deferred
commencement conditions have been satisfied, the consent will become operative
from the date of that written notification, subject to the conditions of
consent, as detailed in Part B - Conditions of Consent (Once the Consent is
Operational).
The application was approved for the following reasons:
(A) The development, subject to a deferred commencement consent, will align with the requirements of the whole of site consent, D/2016/476.
(B) The development, subject to conditions, is consistent with the objectives of the B4 Mixed Use zone.
(C) The development will not adversely affect the character of the Darlinghurst West locality.
(D) The development is compatible with and will not adversely impact the State Heritage item (00461) 'St John's Church and Rectory', or the 'Oxford Street and Victoria Street' (C12) Heritage Conservation Area.
(E) The proposed signage, subject to conditions, is in keeping with the existing signage strategy of the premise and is compatible with the built form and locality.
(F) The development, subject to conditions, will maintain orderly operations, safety and management of the premise.
(G) The development, subject to conditions, is identified as an in-demand community service for at-risk persons, which is complementary to existing service providers in the local area.
(H) The development, subject to conditions, satisfies the requirements of design excellence.
(I) The development will not unreasonably compromise the amenity of the nearby properties.
(J) The development accords with objectives of relevant planning controls.
(K) Condition 1(a) was amended to avoid delays to the conservation works.
Carried unanimously
D/2022/425
Report author: Sarah Anderson
Publication date: 22/02/2023
Date of decision: 22/02/2023
Decided at meeting: 22/02/2023 - Local Planning Panel
Accompanying Documents: