Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee
Decision status: Recommendations Determined
2023/113002
Recommendation
It is recommended that the Committee endorse the
temporary road
(A) The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.
(B) The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.
(C) There is currently no contingency date proposed as the proposed road closure dates are governed by the Sydney Light Rail shutdown. In the event, the works are postponed, the proposed road closure will be rescheduled to align with the next Sydney Light Rail shutdown.
(D) The
Applicant must contact the
(E) The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.
(F) The
Applicant must provide a telephone number of the supervisor responsible for the
proposed
(G) The
Applicant must contact Sydney Buses and arrange and pay for the rerouting of
bus services around the
Voting
Members for this Item
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Transport for NSW |
ü |
|
NSW Police – |
ü |
|
Representative for the Member for |
ü |
|
Place Management New South Wales |
ü |
|
Advice
The Committee unanimously supported the recommendation.
Background
Mirvac has applied
for the temporary road
Report author: Ganesh Vengadasalam
Publication date: 16/03/2023
Date of decision: 16/03/2023
Decided at meeting: 16/03/2023 - Local Pedestrian, Cycling and Traffic Calming Committee