Decision Maker: Local Planning Panel
Decision status: Recommendations Determined
The Panel granted consent to Development Application
Number strikethrough):
(10) PLAN
OF MANAGEMENT – SEX SERVICES PREMISES
The use must always be operated and managed in
accordance with the Plan of Management (as amended by Condition 3 of this
consent), prepared by ABC Planning Pty Ltd and in consultation with Urban
Realists Planning and Health Consultants dated November 2013, that has been
approved by Council (Council Reference: 2023/080188).
Should there be any additional or altered
activities/procedures to those specified in the approved plan of management
that remain within the scope of the development consent, or change of
ownership or management, then the plan of management must be
appropriately reviewed and submitted to and approved by Council.
In the event of any inconsistency, the conditions
of this consent will prevail over the Plan of Management.
Reason
To ensure all parties are aware of the approved
supporting documentation that applies to the development.
The application was approved for the following reasons:
(A) The development is consistent with the objectives of the SP5 Metropolitan Centre Zone as it promotes the primary role of the zone as a centre for employment, contributes towards commercial opportunities, as well as the diversity of compatible land uses within Sydney.
(B) The proposal generally satisfies the objectives and provisions of the Sydney Local Environmental Plan 2012 including Clause 7.21 (Location of Sex Services Premises), and subject to conditions, will not create adverse amenity impacts nor cause disturbance in the neighbourhood.
(C) The proposal is consistent with the relevant objectives of the Sydney Development Control Plan 2012.
(D) The proposal is consistent with the permissible hours of operation of Section 3.15.4 of Sydney Development Control Plan 2012 and accords with Section 4.4.6 of Sydney Development Control Plan 2012 for sex services premises.
(E) Subject to the recommended conditions of consent, the proposed development will maintain the existing level of amenity currently obtained for the site locality and adjoining sites and will not result in additional adverse environmental impacts. Conditions of consent are recommended to ensure the use continues to be managed in appropriate manner in accordance safe practices and the procedures outlined within the endorsed Plan of Management.
(F) Condition 10 was amended to clarify that the Plan of Management remains in effect if the ownership or management of the premises changes.
Carried unanimously.
D/2023/92
Report author: Jessica Joseph
Publication date: 02/07/2023
Date of decision: 28/06/2023
Decided at meeting: 28/06/2023 - Local Planning Panel
Accompanying Documents: