Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee
Decision status: Recommendations Determined
2023/385575
Recommendation
It is recommended that the Committee endorse the
temporary road
· from 7.30am on Monday 28 August 2023 to 5.30pm on Wednesday 30 August 2023, with contingency dates of 4 to 6 September 2023, 11 to 13 September 2023, 18 to 20 September 2023 and 25 to 27 September 2023
This closure is for the removal of the tower crane No 3.
· from 7.30am on Monday 11 September 2023 to 5.30pm on Friday 15 September 2023, with contingency dates of 18 to 20 September 2023, 25 to 27 September 2023, 2 to 6 October and 9 to 10 October 2023
This closure is for the installation of steel and glass for Oculus.
subject to the following conditions:
(A) The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.
(B) The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.
(C) The Applicant has indicated the above dates as contingency dates.
(D)
The Applicant must contact the
(E) The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.
(F)
The Applicant must provide a telephone number of
the supervisor responsible for the proposed
(G) The Applicant must provide TfNSW-Accredited Traffic Controllers to safely manage the 24 Hours continuous road closure
Voting
Members for this Item
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Transport for NSW |
ü |
|
NSW Police – |
ü |
|
Representative for the Member for |
ü |
|
Advice
The Committee unanimously supported the recommendation.
Background
Toga Constructions NSW Pty Ltd has applied for the
temporary road
· from 7.30am on Monday 28 August 2023 to 5.30pm on Wednesday 30 August 2023, with contingency dates of 4 to 6 September, 11 to 13 September, 18 to 20 September and 25 to 27 September 2023
This closure is for the removal of the tower crane No 3.
· from 7.30am on Monday 11 September 2023 to 5.30pm on Friday 15 September 2023, with contingency dates of 18 to 20 September and 25 to 29 September 2023, 2 to 6 October and 9 to 13 October 2023.
This closure is for the installation of steel and glass for
Oculus
Report author: Claudia Calabro
Publication date: 20/07/2023
Date of decision: 20/07/2023
Decided at meeting: 20/07/2023 - Local Pedestrian, Cycling and Traffic Calming Committee
Accompanying Documents: