Decision Maker: Local Planning Panel
Decision status: Recommendations Determined
The Panel granted consent to Development
Application Number strikethrough):
(2) DESIGN MODIFICATION – APT RELOCATION
The proposed APT is not approved to be installed in the currently proposed location.
The
proposed APT is to be relocated to the eastern side of the basketball court
entrance gates on Sydney Place, adjacent to the retaining wall between Sydney
Place and the basketball court.
A plan showing the precise location of the
relocated APT is to be submitted to and approved by Council’s Area Planning
Manager prior to the issue of a Construction Certificate.
The
submitted plan must provide dimensions confirming the precise location of the
APT to comply with the following:
-
The
distance between the nearest part of the APT and the most eastern side of the
basketball court entry gates is to be 2 metres.
-
A 600mm
1000mm clearance is to be provided between the north rear
elevation of the APT and the adjacent retaining wall between the basketball
courts and Sydney Place.
Reason
To require the proposed APT to be situated to a more suitable and appropriate location on Sydney Place.
(10)
HOURS OF OPERATION
(a) The
approved base hours of operation of the facility are from sunrise to 9:00pm.
(b) Notwithstanding
(a) above, a trial period is granted for the operation of the facility from
9:00pm to sunrise for a period of twelve months.
Remaining conditions to be renumbered accordingly.
Reasons for Decision
The application was approved for the
following reasons:
(A)
The development, subject to conditions, serves the
public interest as it will provide an essential community facility serving an
outdoor recreation area and will enhance the amenity of the local area.
(B)
The
relocation of the facility as outlined in Condition 2 addresses residents’
concerns about security, lighting and amenity.
(C)
The
proposal satisfies the objectives of the Environmental Planning and Assessment
Act 1979, in that, subject to the imposition of appropriate conditions as
recommended, it achieves the objectives of the planning controls for the site
for the reasons outlined in the report to the Local Planning Panel.
(D)
The
development, subject to conditions, is consistent with the objectives of the
RE1 Public Recreation zone under the Sydney Local Environment Plan 2012.
(E)
Appropriate
conditions are recommended to ensure the proposed development does not
adversely impact upon the heritage significance of nearby sites.
(F)
Appropriate
conditions are recommended to ensure the proposed development will be
effectively maintained and kept clean.
(G)
The
development accords with the objectives of relevant planning controls.
(H)
Subject
to recommended conditions of consent, the development satisfies the Design
Excellence provisions pursuant to Clause 6.21C of the Sydney Local
Environmental Plan 2012.
(I)
The public
interest is served by the approval of the proposal, as additional information
to the development application has addressed the matters raised by the City and
the community, subject to recommended conditions.
(J)
Condition
2 was amended to enable access for servicing of the facility.
(K)
Condition
10 was added to address residents’ concerns.
Carried unanimously.
D/2022/431
Report author: Daniel Stanley
Publication date: 12/09/2023
Date of decision: 06/09/2023
Decided at meeting: 06/09/2023 - Local Planning Panel
Accompanying Documents: