Mobile Crane - Temporary Road Closures - Fitzgerald Street and Brown Street, Newtown

Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee

Decision status: Recommendations Determined

Decisions:

2023/530602

Recommendation

It is recommended that the Committee endorse the temporary road closures of Fitzgerald Street, Newtown, between Rochester Street and dead end of Fitzgerald Street, (four lanes) and Brown Street, between Church Street and Fitzgerald Street, (three lanes), from 7.30am to 5.30pm on Thursday 23 November 2023, subject to the following conditions:

(A)       The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.

(B)       The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.

(C)       The Applicant has indicated the 30 November 2023 as a contingency date.

(D)       The Applicant must contact the Inner West PAC  to discuss deployment of user pay police for the road closure.

The Applicant must provide a telephone number of the supervisor responsible for the proposed closure and include contact details in the notification letters to be distributed to affected stakeholders.

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

Transport for NSW

ü

NSW Police – Inner West PAC

ü

Representative for the Member for Newtown

ü

 

Advice

The Committee unanimously supported the recommendation.

Background

Sheeth Pty Ltd has applied for the temporary road closures of Fitzgerald Street, Newtown, between Rochester Street and dead end of Fitzgerald Street, (four lanes) and Brown Street, between Church Street and Fitzgerald Street, (three lanes), from 7.30am to 5.30pm on Thursday 23 November 2023.

Report author: Claudia Calabro

Publication date: 19/10/2023

Date of decision: 19/10/2023

Decided at meeting: 19/10/2023 - Local Pedestrian, Cycling and Traffic Calming Committee