Decision Maker: Local Planning Panel
Decision status: Recommendations Determined
The Panel:
(A) upheld the variation requested to the car parking spaces non-discretionary development standard in accordance with Clause 4.6 'Exceptions to development standards' of the Sydney Local Environmental Plan 2012; and
(B) granted
consent to Development Application Number strikethrough):
6(A)Â DESIGN MODIFICATION
The proposed northern and eastern elevation
windows are to be modified to be clear glazing with privacy to be managed via
internal blinds
Reason
To
ensure adequate internal amenity.
(7) FLOOD PLANNING LEVELS
The
development must be constructed to comply with the recommended flood planning
levels indicated in Section 4.5 of the report titled Flood Study prepared by
MBC Engineering dated 2 December 2023.
Details
must be submitted to the
Registered Certifier prior to the issue of any Construction Certificate
demonstrating that the development will comply with the recommended flood
planning levels (33.25 mAHD).
Reason
To ensure the development complies with the
recommended flood planning levels.
The application was approved for the following reasons:
(A) The proposed development is permitted with consent in the R1 General Residential zone.
(B) The development exhibits design excellence under Clause 6.21C of Sydney Local Environmental Plan 2012.
(C) The development responds appropriately to the scale of surrounding buildings and is compatible with the character of the Prince Alfred Park South locality and the Redfern Estate heritage conservation area.
(D) The development will not unreasonably compromise the amenity of neighbouring properties, including demand for on-street car parking.
(E) The development is generally consistent with the objectives of Chapter 3 Part 1 of State Environmental Planning Policy (Housing) 2021, Sydney Local Environmental Plan 2012 and Sydney Development Control Plan 2012.
(F) Based
upon the material available to the
(G) Condition 6A was added to ensure adequate internal amenity.
(H) Condition 7 was modified to specify the flood planning level.
Carried unanimously.
D/2024/477
Report author: Georgia McKenzie
Publication date: 09/09/2024
Date of decision: 04/09/2024
Decided at meeting: 04/09/2024 - Local Planning Panel
Accompanying Documents: