Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee
Decision status: Recommendations Determined
2024/501504
Recommendation
It is recommended that the Committee endorse the
(A)
The Applicant must comply with the Works Zone
conditions as stipulated in Schedule C of this agenda.
(B) The Applicant must obtain separate approval from the City's Tree Management Team prior to implementation of the Works Zone.
(C) The Applicant must notify adjacent properties of the Works Zone at least 14 days prior to installation and must provide a telephone number of the supervisor responsible for the proposed Works Zone and include contact details in the notification letter to be distributed to affected stakeholders.
(D) The Applicant must advise if the Construction Traffic Management Plan (CTMP) has been approved and ensure all conditions within the CTMP are adhered to.
(E) The Works Zone is limited to construction vehicles up to 12.5 metres long only.
Voting
Members for this Item
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Transport for NSW |
ü |
|
NSW Police – |
ü |
|
Representative for the Member for |
ü |
|
Advice
The Committee unanimously supported the recommendation.
Background
Buildcorp Group Pty Ltd has requested
The Works Zone is to facilitate construction works at 1 Kent
Street, Millers Point.
Report author: Ganesh Vengadasalam
Publication date: 10/10/2024
Date of decision: 10/10/2024
Decided at meeting: 10/10/2024 - Local Pedestrian, Cycling and Traffic Calming Committee
Accompanying Documents: