Works Zone - Macleay Street, Potts Point

Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee

Decision status: Recommendations Determined

Decisions:

2024/568059

Recommendation

It is recommended that the Committee endorse the reallocation of the kerb space on the western side of Macleay Street, Potts Point, between the points 20 metres and 40 metres north of Challis Avenue as "Works Zone 7.30am-5.30pm Mon-Fri 7.30am-3.30pm Sat" and "1P 5.30-10pm Mon-Fri 3.30-10pm Sat 8am-10pm Sun & Public Holidays Permit Holders Excepted Area 19", subject to the following conditions:

(A)      The Applicant must comply with the Works Zone conditions as stipulated in Schedule C of this agenda.

(B)      The Applicant must obtain separate approval from the City's Tree Management Team prior to implementation of the Works Zone.

(C)      The Applicant is not permitted to operate any part of a crane over a public road or hoist/swing goods from a Works Zone across or over any part of a public road by means of a lift, hoist or crane unless a separate approval has been obtained from the City's Construction and Building Certification Services Unit as required under Section 68 of the Local Government Act 1993 and Section 138 of the Roads Act 1993.

(D)      The Applicant must notify adjacent properties of the Works Zone at least 14 days prior to installation and must provide a telephone number of the supervisor responsible for the proposed Works Zone and include contact details in the notification letter to be distributed to affected stakeholders.

(E)      The Applicant must advise if the Construction Traffic Management Plan (CTMP) has been approved and ensure all conditions within the CTMP are adhered to.

(F)       The Works Zone is limited to construction vehicles up to 12.5m long.

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Transport for NSW

ü

 

NSW Police – Kings Cross PAC

ü

 

Representative for the Member for Sydney

ü

 

 

Advice

The Committee unanimously supported the recommendation.

Background

A d & b Pty Ltd has requested a 20 metre long Works Zone in Macleay Street, Potts Point.

The Works Zone is to facilitate construction works at 55-63 Macleay Street, Potts Point.

Report author: Ganesh Vengadasalam

Publication date: 14/11/2024

Date of decision: 14/11/2024

Decided at meeting: 14/11/2024 - Local Pedestrian, Cycling and Traffic Calming Committee

Accompanying Documents: