Mobile Crane - Temporary Road Closure - Eveleigh Street, Redfern

Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee

Decision status: Recommendations Determined

Decisions:

2018/552009

Recommendation

It is recommended that the Committee endorse the temporary road closure of Eveleigh Street, Redfern, between Hudson and Cleveland Streets, on Wednesday 27 February 2019, from 7am to 5pm, subject to the following conditions:

(A)      The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.

(B)      The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.

(C)      The Applicant has indicated Wednesday 6 March 2019 as a contingency date.

(D)      The Applicant must contact the Redfern PAC to discuss deployment of user pay police for the road closure.

(E)      The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.

(F)       The Applicant must provide a telephone number of the supervisor responsible for the proposed closure and include contact details in the notification letters to be distributed to affected stakeholders.

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Roads and Maritime Services

ü

 

NSW Police – Redfern PAC

ü

 

Representative for the Member for Newtown

ü

 

 

Decision

The Committee carried the recommendation unanimously.

Background

Cubic Contracting NSW Pty Ltd has applied for the temporary road closure of Eveleigh Street, Redfern, between Hudson and Cleveland Streets, on Wednesday 27 February 2019, from 7am to 5pm.

Report author: Tony Ly

Publication date: 31/12/2018

Date of decision: 13/12/2018

Decided at meeting: 13/12/2018 - Local Pedestrian, Cycling and Traffic Calming Committee