Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee
Decision status: Recommendations Determined
2019/527081
Recommendation
It is recommended that the Committee endorse the
(A) The Applicant must comply with the Works Zone conditions as stipulated in Schedule C of this agenda.
(B) The Applicant is not permitted to operate any part of a crane over a public road or hoist/swing goods from a Works Zone across or over any part of a public road by means of a lift, hoist or crane unless a separate approval has been obtained from the City's Construction and Building Certification Services Unit as required under Section 68 of the Local Government Act 1993 and Section 138 of the Roads Act 1993.
(C) The Applicant must temporarily remove the existing layback along the Waterloo Street frontage of 72-84 Foveaux Street, Surry Hills to provide sufficient space for vehicles to load and unload within the Works Zone, as well as maintain at least 3 metre travel lane for vehicular access in Waterloo Street.
(D) The Applicant must fully fund, and deliver, the reinstatement of kerb and gutter and footpath along the Waterloo Street frontage of 72-84 Foveaux Street, Surry Hills, to the City's satisfaction, once the Works Zone is no longer required. All works must be undertaken to the City’s standards and specifications and to the satisfaction of the City’s Public Domain team.
(E) The Works Zone is to be limited to vehicles up to 8.8 metre long Rigid Vehicles
(F) The Applicant must notify adjacent properties of the Works Zone at least 14 days prior to installation and must provide a telephone number of the supervisor responsible for the proposed Works Zone and include contact details in the notification letter to be distributed to affected stakeholders.
Voting
Members for this Item
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Roads and Maritime Services |
ü |
|
NSW Police – |
ü |
|
Representative for the Member for |
ü |
|
Advice
The Committee unanimously supported the recommendation.
Background
Infinity Construction Group Pty Ltd has requested
The Works Zone is to facilitate construction works at 72-84
Foveaux Street, Surry Hills.
Report author: Hassan Choudhry
Publication date: 12/12/2019
Date of decision: 12/12/2019
Decided at meeting: 12/12/2019 - Local Pedestrian, Cycling and Traffic Calming Committee