Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee
Decision status: Recommendations Determined
2020/279071
Recommendations
It is recommended that the
Committee endorse the temporary road closures of Caroline and Louis Streets,
Redfern, between Eveleigh Street and Vine Street as follows:
·
Stormwater Works from 7am to 6pm from Monday 31
August 2020 to Saturday 5 September 2020, roads to be reopened to traffic after hours,
Contingency Dates
from Monday 7 September 2020 to Saturday 12 September 2020
·
Public Domain Works - Caroline Street works
occurring from Monday 7 September 2020 to Saturday 19 September 2020, road to
remain closed for the duration,
Contingency Dates
from Sunday 20 September 2020 to Saturday 10 October 2020,
·
Public Domain Works - Louis Street works
occurring from 7am to 6pm from Monday 12 October 2020 to Saturday 17 October
2020, roads to be reopened to traffic after hours,
Contingency Dates from Monday 19
October 2020 to Saturday 24 October 2020.
Subject to the following
conditions:
(A)
The Applicant must comply with the temporary
road closure conditions as mentioned in Schedule B of this agenda.
(B)
The Applicant must comply with any other
conditions imposed by City’s Construction Regulation Unit.
(C)
The Applicant has indicated the above dates as
contingency dates.
(D)
The Applicant must contact the South Sydney PAC
to discuss deployment of user pay police for the road closures.
(E)
The Applicant must provide a telephone number of
the supervisor responsible for the proposed closure and include contact details
in the notification letters to be distributed to affected stakeholders.
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Transport for NSW |
ü |
|
NSW Police – South Sydney PAC |
ü |
|
Representative for the Member for
Newtown |
ü |
|
Advice
Advice will be updated after the meeting.
Background
Deicorp
Constructions has applied for the temporary road
·
Stormwater
Works from 7am to 6pm from Monday 31 August 2020 to Saturday 5 September 2020,
roads to be reopened to traffic after hours,
·
Contingency
Dates from Monday 7 September 2020 to Saturday 12 September 2020
·
Public
Domain Works - Caroline Street works occurring from Monday 7 September 2020 to
Saturday 19 September 2020, road to remain closed for the duration,
·
Contingency
Dates from Sunday 20 September 2020 to Saturday 10 October 2020,
·
Public
Domain Works - Louis Street works occurring from 7am to 6pm from Monday 12
October 2020 to Saturday 17 October 2020, roads to be reopened to traffic after
hours,
·
Contingency
Dates from Monday 19 October 2020 to Saturday 24 October 2020.
Report author: Claudia Calabro
Publication date: 20/08/2020
Date of decision: 20/08/2020
Decided at meeting: 20/08/2020 - Local Pedestrian, Cycling and Traffic Calming Committee
Accompanying Documents: