Road Works - Temporary Road Closures - Caroline and Louis Streets, Redfern

Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee

Decision status: Recommendations Determined

Decisions:

2020/279071

Recommendations

It is recommended that the Committee endorse the temporary road closures of Caroline and Louis Streets, Redfern, between Eveleigh Street and Vine Street as follows:

·                Stormwater Works from 7am to 6pm from Monday 31 August 2020 to Saturday 5 September 2020, roads to be reopened to traffic after hours,

Contingency Dates from Monday 7 September 2020 to Saturday 12 September 2020

·                Public Domain Works - Caroline Street works occurring from Monday 7 September 2020 to Saturday 19 September 2020, road to remain closed for the duration,

Contingency Dates from Sunday 20 September 2020 to Saturday 10 October 2020,

·                Public Domain Works - Louis Street works occurring from 7am to 6pm from Monday 12 October 2020 to Saturday 17 October 2020, roads to be reopened to traffic after hours,

Contingency Dates from Monday 19 October 2020 to Saturday 24 October 2020.

Subject to the following conditions:

(A)      The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.

(B)      The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.

(C)      The Applicant has indicated the above dates as contingency dates.

(D)      The Applicant must contact the South Sydney PAC to discuss deployment of user pay police for the road closures.

(E)      The Applicant must provide a telephone number of the supervisor responsible for the proposed closure and include contact details in the notification letters to be distributed to affected stakeholders.

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Transport for NSW

ü

 

NSW Police – South Sydney PAC

ü

 

Representative for the Member for Newtown

ü

 

Advice

Advice will be updated after the meeting.

Background

Deicorp Constructions has applied for the temporary road closures of Caroline and Louis Streets, Redfern, between Eveleigh Street and Vine Street as follows:

·                Stormwater Works from 7am to 6pm from Monday 31 August 2020 to Saturday 5 September 2020, roads to be reopened to traffic after hours,

·                Contingency Dates from Monday 7 September 2020 to Saturday 12 September 2020

·                Public Domain Works - Caroline Street works occurring from Monday 7 September 2020 to Saturday 19 September 2020, road to remain closed for the duration,

·                Contingency Dates from Sunday 20 September 2020 to Saturday 10 October 2020,

·                Public Domain Works - Louis Street works occurring from 7am to 6pm from Monday 12 October 2020 to Saturday 17 October 2020, roads to be reopened to traffic after hours,

·                Contingency Dates from Monday 19 October 2020 to Saturday 24 October 2020.

 

Report author: Claudia Calabro

Publication date: 20/08/2020

Date of decision: 20/08/2020

Decided at meeting: 20/08/2020 - Local Pedestrian, Cycling and Traffic Calming Committee

Accompanying Documents: