Project Scope - Cardigan Street Reserve Upgrade, Glebe

Decision Maker: Council

Decision status: Recommendations Determined

Decisions:

X019550.003

It is resolved that Council:

(A)      endorse the scope of work for improvements to Cardigan Street Reserve as described in the subject report and shown in the concept design as Attachment B to the subject report, for progression to relevant approvals, preparation of construction documentation, tender and construction; and

note the estimated project forecast as outlined in Confidential Attachment D to the subject report.

Report author: Belinda Graham

Publication date: 19/08/2019

Date of decision: 19/08/2019

Decided at meeting: 19/08/2019 - Council

Accompanying Documents: