Works Zone - Marsden Street, Camperdown

Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee

Decision status: Recommendations Determined

Decisions:

2022/399393

Recommendation

It is recommended that the Committee endorse the reallocation of the kerb space on the southern side of Marsden Street, Camperdown, between the points 15.2 metres and 25.2 metres west of Missenden Road as "Works Zone 7.30am- 5.30pm, Mon- Fri 7.30am-3.30pm Sat" and "No Stopping All Other Times", subject to the following conditions:

(A)      The Applicant must comply with the Works Zone conditions as stipulated in Schedule C of this agenda.

(B)      The Applicant is not permitted to operate any part of a crane over a public road or hoist/swing goods from a Works Zone across or over any part of a public road by means of a lift, hoist or crane unless a separate approval has been obtained from the City's Construction and Building Certification Services Unit as required under Section 68 of the Local Government Act 1993 and Section 138 of the Roads Act 1993.

(C)      The Applicant must provide TfNSW-Accredited Traffic Controllers to safely manage the operation of the Works Zone and maintain local vehicular access in Marsden Street at all times. If approaching traffic or vehicles exiting/entering driveways opposite cannot pass a vehicle in the Works Zone, the TfNSW-Accredited Traffic Controllers must instruct the construction vehicle to depart the Works Zone immediately.

(D)      The Applicant must notify adjacent properties of the Works Zone at least 14 days prior to installation and must provide a telephone number of the supervisor responsible for the proposed Works Zone and include contact details in the notification letter to be distributed to affected stakeholders.

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Transport for NSW

ü

 

NSW Police – Inner West PAC

ü

 

Representative for the Member for Newtown

ü

 

 

Advice

The Committee unanimously supported the recommendation.

Background

Citywide Constructions has requested a 10 metre long Works Zone in Marsden Street, Camperdown.

The Works Zone is to facilitate construction works at 21 Missenden Road, Camperdown.

Report author: Vicki Calleja

Publication date: 15/09/2022

Date of decision: 15/09/2022

Decided at meeting: 15/09/2022 - Local Pedestrian, Cycling and Traffic Calming Committee

Accompanying Documents: