Decision Maker: Council
Decision status: Recommendations Determined
It is resolved that:
(A)
Council note that the updated extensive flood modelling for the Ashmore Precinct
Trunk Stormwater Project confirms the significant stormwater works, already
undertaken and to be undertaken as part of the redevelopment of the Ashmore
precinct, will significantly reduce flooding in the precinct;
(B) Council note that the Concept Design Report in Confidential Attachment C to the subject report has recommended the scope include construction of a large inlet structure on Coulson Street, Transition Structure within 165-175 Mitchell Road, culvert improvements on Euston Road and short-term flap gate(s) installation along Burrows Road, Erskineville. This reduced scope will still meet the original objectives of the Project;
(C)
Council approve the substantive terms of
the draft contract variation, set out in Annexure 1
to the Original Ashmore Project Agreement between the City and Sydney Water
Corporation for the Ashmore Precinct Trunk Stormwater Project, as detailed in
Confidential Attachment B to the subject report;
(D)
Council note
that, as detailed in Confidential Attachment B to the subject report, on
execution of the contract variation, the new scope will be split between the
parties for delivery. Sydney Water will engage third party service providers
for their works and the City will complete their works under an existing
Voluntary Planning Agreement (VPA);
(E)
Council note
that, as detailed in Confidential Attachment B to the subject report, Sydney
Water will reimburse the City's costs on the project to date to offset Green
Square Trunk Drain descoped works, Sydney Water will deliver all scope not covered
by an existing VPA and both parties will cover their own costs after execution;
(F) Council not invite tenders for the City's works in accordance with the tendering requirements set out in section 55 of the Local Government Act 1993 as the work will be completed under an existing Voluntary Planning Agreement; and
(G) authority be delegated to the Chief Executive Officer to finalise negotiations, execute and administer the contract variation to the Original Ashmore Project Agreement, based on terms substantially the same as the terms shown at Confidential Attachment B to the subject report.
Carried unanimously.
X008356.006
Report author: Samantha Carroll
Publication date: 31/10/2022
Date of decision: 31/10/2022
Decided at meeting: 31/10/2022 - Council