Works Zone - Dick Street, Chippendale

Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee

Decision status: Recommendations Determined

Decisions:

2023/214362

Recommendation

It is recommended that the Committee endorse the reallocation of the kerb space on the northern side of Dick Street, Chippendale, between the points 37.6 metres and 49.6 metres east of Abercrombie Street as "Works Zone 7.30am-5.30pm Mon-Fri, 7.30am-3.30pm Sat" and "2P Ticket 5.30-10pm Mon-Fri, 3.30-10pm Sat, 8am-10pm Sun, Permit Holders Excepted Area 32", subject to the following conditions:

(A)      The Applicant must comply with the Works Zone conditions as stipulated in Schedule C of this agenda.

(B)      The Applicant must obtain separate approval from the City's Tree Management Team prior to implementation of the Works Zone.

(C)      The Works Zone is to be limited to Small Rigid Vehicles (SRV) up to 6.4 metre long.

(D)      The Applicant must reinstate the temporary removal of garden bed when the Works Zone is removed.

(E)      The Applicant is not permitted to operate any part of a crane over a public road or hoist/swing goods from a Works Zone across or over any part of a public road by means of a lift, hoist or crane unless a separate approval has been obtained from the City's Construction and Building Certification Services Unit as required under Section 68 of the Local Government Act 1993 and Section 138 of the Roads Act 1993.

(F)       The Applicant must notify adjacent properties of the Works Zone at least 14 days prior to installation and must provide a telephone number of the supervisor responsible for the proposed Works Zone and include contact details in the notification letter to be distributed to affected stakeholders.

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Transport for NSW

ü

 

NSW Police – South Sydney PAC

ü

 

Representative for the Member for Newtown

ü

 

 

Advice

The Committee unanimously supported the recommendation.

Background

Infinity Constructions has requested a 12 metre long Works Zone in Dick Street, Chippendale.

The Works Zone is to facilitate construction works at 8B Dick Street, Chippendale.

Report author: Terry Xu

Publication date: 18/05/2023

Date of decision: 18/05/2023

Decided at meeting: 18/05/2023 - Local Pedestrian, Cycling and Traffic Calming Committee

Accompanying Documents: