Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee
Decision status: Recommendations Determined
2024/282529
Recommendation
It is recommended that the Committee endorse the
(A) The Applicant must comply with the Works Zone conditions as stipulated in Schedule C of this agenda.
(B) The Applicant is not permitted to operate any part of a crane over a public road or hoist/swing goods from a Works Zone across or over any part of a public road by means of a lift, hoist or crane unless a separate approval has been obtained from the City's Construction and Building Certification Services Unit as required under Section 68 of the Local Government Act 1993 and Section 138 of the Roads Act 1993.
(C) The Applicant must notify adjacent properties of the Works Zone at least 14 days prior to installation and must provide a telephone number of the supervisor responsible for the proposed Works Zone and include contact details in the notification letter to be distributed to affected stakeholders.
(D) The Applicant must not reverse onto Hosking Place from Castlereagh Street. The Applicant must enter and exit Hosking Place from Castlereagh Street in a forward direction only.
(E) The Applicant must provide TfNSW-Accredited Traffic Controllers to safely manage the operation of the Works Zone and ensure construction vehicles are parked within the allocated kerb space. If approaching traffic cannot pass a vehicle in the Works Zone, the TfNSW Accredited Traffic Controllers must instruct the construction vehicle to depart the Works Zone immediately.
Voting
Members for this Item
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Transport for NSW |
ü |
|
NSW Police – |
ü |
|
Representative for the Member for |
ü |
|
Advice
The Committee unanimously supported the recommendation and
noted the change to the reallocation of the kerb space on the northern side of
Hosking Place, Sydney, between the points
54 metres and 64 metres west of Castlereagh Street as "Works Zone 7am-7pm
Mon-Fri 7am-5pm Sat" and "No Parking All Other Times.
Background
Max Build Pty has requested
The Works Zone is to facilitate construction works at 1
Hosking Place, Sydney.
Report author: Chin Gupta
Publication date: 13/06/2024
Date of decision: 13/06/2024
Decided at meeting: 13/06/2024 - Local Pedestrian, Cycling and Traffic Calming Committee
Accompanying Documents: