Project Scope - Hollis Park Playground Upgrade, Newtown

Decision Maker: Council

Decision status: Recommendations Determined

Decisions:

X019487

It is resolved that Council:

(A)      endorse [KA1] [KA2] the scope of work for improvements to Hollis Park Playground, as described in the subject report and shown in the Final Concept Plan as Attachment B to the subject report, for progression to preparation of relevant approvals, construction documentation, tender and construction; and

note the estimated project forecast and that additional funding is required to complete the project as outlined in Confidential Attachment D to the subject report.

 


 [KA1]Who is it proposed to endorse this - Council, Committee, etc

 [KA2]Added 'Council' to the line above.

Report author: Emma Cosgrove

Publication date: 19/08/2019

Date of decision: 19/08/2019

Decided at meeting: 19/08/2019 - Council