Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee
Decision status: Recommendations Determined
2021/032125
Recommendation
It is recommended that the Committee endorse the
temporary road
(A) The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.
(B) The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.
(C) The Applicant has indicated the 4 April, 9 May and 23 May 2021 as contingency dates.
(D)
The Applicant must contact the
(E) The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.
(F)
The Applicant must provide a telephone number of
the supervisor responsible for the proposed
(G)
The Applicant must contact Sydney Buses and
arrange and pay for the rerouting of bus services around the
Voting
Members for this Item
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Transport for NSW |
ü |
|
NSW Police – |
ü |
|
Representative for the Member for |
ü |
|
Advice
The Committee unanimously supported the
recommendation and noted the change of dates for the Temporary Road Closure –
Castlereagh Street, Sydney between Hunter and King Streets, Sydney as follows:
From: 2am to 7pm on Sunday 28 March 2021, Sunday 2 May 2021 and Sunday 16 May
2021, with contingency dates of 4 April, 9 and 23 May 2021
To: 2am
to 7pm on Sunday 11 April 2021, Sunday
2 May 2021 and Sunday 16 May 2021 with contingency dates of 18th
April 2021, 9 May 2021 and 23 May 2021
Background
Jarrah Construction Services has applied for the temporary
road
Report author: Claudia Calabro
Publication date: 18/03/2021
Date of decision: 18/03/2021
Decided at meeting: 18/03/2021 - Local Pedestrian, Cycling and Traffic Calming Committee
Accompanying Documents: