Project Scope - King Street Cycleway - Pitt Street to Phillip Street

Decision Maker: Council

Decision status: Recommendations Determined

Decision:

It is resolved that Council:

(A)      approve the concept design for the King Street Cycleway, between Pitt Street and Phillip Street, as shown in Attachment B to the subject report, for progression to final design and construction;

(B)      note the estimated project costs as detailed in confidential Attachment D to the subject report; and

(C)      note that the City has accepted a funding offer from the NSW government as part of the Transport for NSW Federal Road Safety Stimulus Program for the design and construction of the project, conditional on the works being completed in the 2021/22 financial year.

Carried unanimously.

S084591

 

Report author: Brendon Hunter

Publication date: 21/02/2022

Date of decision: 21/02/2022

Decided at meeting: 21/02/2022 - Council

Accompanying Documents: