Decision Maker: Local Pedestrian, Cycling and Traffic Calming Committee
Decision status: Recommendations Determined
2023/313007
Recommendation
It is recommended that the Committee endorse the
temporary road
(A) The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.
(B) The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.
(C) The Applicant has indicated the 3, 10,17 and, 24 September and 1, 8 and 15 October as contingency dates.
(D) The
Applicant must contact the
(E) The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.
(F) The
Applicant must provide a telephone number of the supervisor responsible for the
proposed
(G) The
Applicant must contact relevant Bus Operators and arrange and pay for the
rerouting of bus services around the
Voting
Members for this Item
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Transport for NSW |
ü |
|
NSW Police – |
ü |
|
Representative for the Member for |
ü |
|
Advice
The Committee unanimously supported the recommendation
Background
Sherington Projects has applied for the temporary road
Report author: Claudia Calabro
Publication date: 17/08/2023
Date of decision: 17/08/2023
Decided at meeting: 17/08/2023 - Local Pedestrian, Cycling and Traffic Calming Committee