Mobile Crane - Temporary Road Closure - James Lane, Sydney

18/07/2019 - Mobile Crane - Temporary Road Closure - James Lane, Sydney

2019/259959

Recommendation

It is recommended that the Committee endorse the temporary road closure of James Lane, Sydney, from 7am to 5pm on Monday 26 August 2019 to Saturday 31 August 2019 subject to the following conditions:

(A)      The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.

(B)      The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.

(C)      The Applicant has indicated 2 September 2019 to 7 September 2019 as contingency dates.

(D)      The Applicant must contact the Sydney City PAC to discuss deployment of user pay police for the road closure.

(E)      The Applicant must provide a telephone number of the supervisor responsible for the proposed closure and include contact details in the notification letters to be distributed to affected stakeholders.

(F)       Police access must be maintained at all times for access to garage area of the Police Station in James Lane.  Applicant to advise Sydney City Police should contingency closures be required.

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Roads and Maritime Services

ü

 

NSW Police – Sydney City PAC

ü

 

Representative for the Member for Sydney

ü

 

 

Advice

The Committee unanimously supported the recommendation.

Background

Icon Pty Ltd has applied for the temporary road closure of James lane, Sydney, from 7am to 5pm on Monday 26 August 2019 to Saturday 31 August 2019.