chevron-rightcancelexternal-link

Works Zone - Riley Street, Surry Hills

15/08/2019 - Works Zone - Riley Street, Surry Hills

2019/302483

Recommendation

It is recommended that the Committee endorse the reallocation of the kerb space on the eastern side of Riley Street, Surry Hills between the points 11 metres and 23.4 metres north of Mackey Street, as 'Works Zone 7.30am-5.30pm Mon-Fri, 7.30am-3.30pm Sat” and “2P Ticket 5.30pm-10pm Mon-Fri, 3.30pm-10pm Sat, Permit Holder Excepted Area 18”, subject to the following conditions:

(A)      The Applicant must comply with the Works Zone conditions as stipulated in Schedule C of this agenda.

(B)      The Applicant must obtain separate approval from the City's Tree Management Team prior to implementation of the Works Zone.

(C)      The Applicant is not permitted to operate any part of a crane over a public road or hoist/swing goods from a Works Zone across or over any part of a public road by means of a lift, hoist or crane unless a separate approval has been obtained from the City's Construction and Building Certification Services Unit as required under Section 68 of the Local Government Act 1993 and Section 138 of the Roads Act 1993.

(D)      The Applicant must notify adjacent properties of the Works Zone at least 14 days prior to installation and must provide a telephone number of the supervisor responsible for the proposed Works Zone and include contact details in the notification letter to be distributed to affected stakeholders.

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Roads and Maritime Services

ü

 

NSW Police – Surry Hills PAC

ü

 

Representative for the Member for Sydney

ü

 

 

Advice

The Committee unanimously supported the recommendation.

Background

Join Constructions has requested a 12.4 metre long Works Zone in Riley Street, Surry Hills.

The Works Zone is to facilitate construction works at 226 Riley Street, Surry Hills.