2020/145527
Recommendation
It is recommended that the Committee endorse the
temporary road
(A) The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.
(B) The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.
(C) The Applicant has indicated the 4-6 July and 11-13 July as contingency dates.
(D)
The Applicant must contact the
(E) The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.
(F)
The Applicant must provide a telephone number of
the supervisor responsible for the proposed
(G)
The Applicant must contact Sydney Buses and
arrange and pay for the rerouting of bus services around the
Voting
Members for this Item
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Transport for NSW |
ü |
|
NSW Police – |
ü |
|
Representative for the Member for |
ü |
|
Advice
The Committee unanimously supported the recommendation and noted the change of time for the temporary road closure of Castlereagh Street, Sydney, between Hunter and King Streets:
from:
·
10pm on Friday 26 June 2020 to 5am on Monday 29
June 2020, with contingency dates of 4-6 July and 11-13 July
to:
· 10pm on Friday 10 July 2020 to 5am on Monday 13 July 2020, with contingency dates of Friday 31 July 2020 to 3 August 2020.
Background
Sydney Metro City & South West has applied for the
temporary road