2020/506895
Recommendation
It is recommended that the Committee note the
(A) Eastern side between the points 0.0 metres and 145.5 metres, north of Bathurst Street, as "No Stopping"; and
(B) Western side between the points 0.0 metres and 145.2 metres, north of Bathurst Street, as "No Stopping".
Voting
Members for this Item
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Transport for NSW |
ü |
|
NSW Police – |
ü |
|
Representative for the Member for |
ü |
|
Advice
The Committee unanimously supported the recommendation.
Background
Transport for NSW’s CBD and South East Light Rail (CSELR) project from Circular Quay to Kingsford and Randwick via Surry Hills started construction on 25 October 2015.
Work has now completed on the CSELR with changes made to the
road network along and next to the light rail corridor such as road closures,
direction of traffic flow, line marking and kerbside parking changes.