Mobile Crane - Temporary Road Closure - King Street, Sydney

15/07/2021 - Mobile Crane - Temporary Road Closure - King Street, Sydney

2021/242575

Recommendation

It is recommended that the Committee endorse the temporary road closure of King Street, Sydney, between Pitt Street and Castlereagh Street, (four lanes), from 9pm to 5am on Saturday 31 July 2021, subject to the following conditions:

(A)       The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.

(B)       The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.

(C)       The Applicant has indicated the 1 August 2021 as a contingency date.

(D)       The Applicant must contact the Sydney City PAC to discuss deployment of user pay police for the road closure.

(E)       The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.

(F)        The Applicant must provide a telephone number of the supervisor responsible for the proposed closure and include contact details in the notification letters to be distributed to affected stakeholders.

 

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Transport for NSW

ü

 

NSW Police – Sydney City PAC

ü

 

Representative for the Member for Sydney

ü

 

 

Advice

The Committee unanimously supported the recommendation.

Background

Forge Venture Management has applied for the temporary road closure of King Street, Sydney, between Pitt Street and Castlereagh Street, (four lanes), from 9pm to 5am on Saturday 31 July 2021.