Project Scope - King Street Cycleway - Pitt Street to Phillip Street

21/02/2022 - Project Scope - King Street Cycleway - Pitt Street to Phillip Street

It is resolved that Council:

(A)      approve the concept design for the King Street Cycleway, between Pitt Street and Phillip Street, as shown in Attachment B to the subject report, for progression to final design and construction;

(B)      note the estimated project costs as detailed in confidential Attachment D to the subject report; and

(C)      note that the City has accepted a funding offer from the NSW government as part of the Transport for NSW Federal Road Safety Stimulus Program for the design and construction of the project, conditional on the works being completed in the 2021/22 financial year.

Carried unanimously.

S084591