Road Works - Temporary Road Closure - Macdonald Street, Erskineville

24/02/2022 - Road Works - Temporary Road Closure - Macdonald Street, Erskineville

2022/012970

Recommendation

It is recommended that the Committee endorse the temporary road closures between 29 February 2022 to 31 May 2022 inclusive, on the following streets in Erskineville:

(A)      Macdonald Street, between Bridge and Hadfields Streets;

(B)      Zenith Street, between Metters and Macdonald Streets;

(C)      Pearl Street, between Metters and Macdonald Streets;

(D)      Eve Street, between Macdonald Street and Coulson Street including Brightwell Lane and Nassau Lane; and

(E)      Goddard Street, south of Macdonald Street.

The closures are subject to the following conditions:

1.         The Applicant must comply with the temporary road closure conditions as mentioned Schedule B of this agenda.

2.         The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.

3.         The Applicant must contact the South Sydney PAC to discuss deployment of user pay police for the road closures.

4.         The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.

5.         The Applicant must provide a telephone number of the supervisor responsible for the proposed closure and include contact details in the notification letters to be distributed to affected stakeholders.

 

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Transport for NSW

ü

 

NSW Police – South Sydney PAC

ü

 

Representative for the Member for Heffron

ü

 

 

Advice

The Committee unanimously supported the recommendation.

Background

On 17 June 2021, the Committee endorsed the temporary road closures for certain streets in Erskineville up until 28 February 2022 for the construction works.

Ward Civil & Environmental Engineering Pty Ltd has applied to extend the period of the closures to 31 May 2022 to allow for the completion of the works which have been delayed due to covid work restrictions and inclement weather.