Mobile Crane - Temporary Road Closure - Seymour Place, Paddington

24/02/2022 - Mobile Crane - Temporary Road Closure - Seymour Place, Paddington

2022/017521

Recommendation

It is recommended that the Committee endorse the temporary road closure of Seymour Place, Paddington, between South Dowling Street and Selwyn Street, (two lanes), from 10am to 1pm on the following Thursdays 17 March 2022, 14 April 2022, 12 May 2020 and 9 June 2022, subject to the following conditions:

(A)      The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.

(B)      The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.

(C)      The Applicant has indicated the 7 July, 4 August, 1 September, 29 September, 27 October, 24 November and 22 December 2022 as contingency dates.

(D)      The Applicant must contact the Surry Hills PAC  to discuss deployment of user pay police for the road closure.

(E)      The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.

(F)       The Applicant must provide a telephone number of the supervisor responsible for the proposed closure and include contact details in the notification letters to be distributed to affected stakeholders.

Voting Members for this Item

 

Voting Members

Support

Object

City of Sydney

ü

 

Transport for NSW

ü

 

NSW Police – Surry Hills PAC

ü

 

Representative for the Member for Sydney

ü

 

 

Advice

The Committee unanimously supported the recommendation.

Background

Adams Traffic Management Services has applied for the temporary road closure of Seymour Place, Paddington, between South Dowling Street and Selwyn Street, (two lanes), from 10am to 1pm on the following Thursdays 17 March 2022, 14 April 2022, 12 May 2020 and 9 June 2022.