Works Zone - Rothschild Avenue, Rosebery

15/06/2023 - Works Zone - Rothschild Avenue, Rosebery

2023/224329

Recommendation

It is recommended that the Committee endorse the allocation of the kerb space on the western side of Rothschild Avenue, Rosebery, between the points 71.3 metres and 85.1 metres north of Morley Avenue as "Works Zone 7.30am-5.30pm Mon-Fri, 7.30am-3.30pm Sat", subject to the following conditions::

(A)      The Applicant must comply with the Works Zone conditions as stipulated in Schedule C of this agenda.

(B)      The Applicant must obtain separate approval from the City's Tree Management Team prior to implementation of the Works Zone.

(C)      The Applicant is not permitted to operate any part of a crane over a public road or hoist/swing goods from a Works Zone across or over any part of a public road by means of a lift, hoist or crane unless a separate approval has been obtained from the City's Construction and Building Certification Services Unit as required under Section 68 of the Local Government Act 1993 and Section 138 of the Roads Act 1993.

(D)      The Applicant must notify adjacent properties of the Works Zone at least 14 days prior to installation and must provide a telephone number of the supervisor responsible for the proposed Works Zone and include contact details in the notification letter to be distributed to affected stakeholders.

(E)      The Works Zone will only be installed upon approval of the Construction Traffic  Management Plan (CTMP).

Voting Members for this Item

Voting Members

Support

Object

City of Sydney

ü

 

Transport for NSW

ü

 

NSW Police – South Sydney PAC

ü

 

Representative for the Member for Heffron

ü

 

 

Advice

The Committee unanimously supported the recommendation.

Background

The owner has requested a 13.8 metre long Works Zone in Rothschild Avenue, Rosebery.

The Works Zone is to facilitate construction works at 72 Rothschild Avenue, Rosebery.