2024/503016
Recommendation
It is recommended that the Committee endorse the
temporary road
(A) The Applicant must comply with the temporary road closure conditions as mentioned in Schedule B of this agenda.
(B) The Applicant must comply with any other conditions imposed by City’s Construction Regulation Unit.
(C) The Applicant has indicated the 7-8 and 14-15 December 2024, as contingency dates.
(D)
The Applicant must contact the
(E) The Applicant is to obtain a Road Occupancy Licence from the Transport Management Centre prior to commencement of works.
(F)
The Applicant must provide a telephone number of
the supervisor responsible for the proposed
(G) The Applicant must maintain local vehicular access to properties fronting Pyrmont Street between Allen and Fig Streets, as well as Pyrmont Street south of Quarry Street.
(H) The Applicant must notify Ian Thorpe Aquatic Centre and the Goldsborough Hotel about the works at least seven days prior to the temporary road closure.
Voting
Members for this Item
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Transport for NSW |
ü |
|
NSW Police – |
ü |
|
Representative for the Member for |
ü |
|
Advice
The Committee unanimously supported the recommendation.
Background
Kane Constructions Pty Ltd has applied for the temporary
road