2018/285383
Recommendation
It is recommended that the
Committee endorse the
(A) The Applicant must comply with the Works Zone conditions as stipulated in Schedule C of this agenda.
(B) The Applicant must obtain separate approval from the City's Tree Management Team prior to implementation of the Works Zone.
(C) The Applicant is not permitted to operate any part of a crane over a public road or hoist/swing goods from a Works Zone across or over any part of a public road by means of a lift, hoist or crane unless a separate approval has been obtained from the City's Construction and Building Certification Services Unit as required under Section 68 of the Local Government Act 1993 and Section 138 of the Roads Act 1993.
(D) The Applicant must notify adjacent properties of the Works Zone at 14 days prior to installation.
(E) The Applicant must provide a telephone number of the Site Manager.
Voting
Members for this Item
Voting Members |
Support |
Object |
City of Sydney |
ü |
|
Roads and Maritime Services |
ü |
|
NSW Police – |
ü |
|
Representative for the Member for |
ü |
|
Decision
The Committee carried the recommendation unanimously.
Background
On 21 June 2017, the Local Pedestrian, Cycling and Traffic Calming Committee (LPCTCC) endorsed a 34 metre long Works Zone on the southern side of Huntley Street, Alexandria east of Euston Lane. The endorsed Works Zone was signposted as "Works Zone 7.30am-5.30pm Mon-Fri, 7.30am-3.30pm Sat".
On 15 March 2018, the LPCTCC endorsed a 35 metre extension to the west of the original Works Zone.
Cockram Construction Australia Pty Ltd has now requested an additional 30m extension to the existing Works Zone in Huntley Street, west of the current location.
The Works Zone extension is to facilitate construction works
at 18 Huntley Street, for a period of approximately 30 weeks.